National distribution
Schools, water sources and WASH blocks were spread across districts, upazilas and engineering offices.
Representative visual · based on supplied DPHE patternClient case study · DPHE · PEDP4
A Tiger One-based management system connected school sites, procurement, contracts, funding, field evidence, water-quality screening, final bills and time extensions for DPHE’s part of the Fourth Primary Education Development Program.
PEDP4 aimed to improve the quality and equity of primary education across Bangladesh. Safe drinking water, gender-segregated WASH facilities and accessible school infrastructure were treated as part of the learning environment—not as isolated construction outputs.
PEDP4 was the government’s primary-education programme. DPHE delivered and monitored the water-supply and sanitation works, while Tiger Park Limited supplied the Tiger One-based digital management system supporting that work.
The management challenge
Schools, water sources and WASH blocks were spread across districts, upazilas and engineering offices.
Site approval, tendering, contracting, allocation, measurement, bills and extensions each required a governed record.
Management needed school-linked photos, water-quality screening and completion evidence alongside financial progress.
Tiger One-based solution
The system provides one management environment spanning site information, audit and accounts, contract and tender information, digital assets, packages, allocation and receipts, water-quality screening, pre-final bills, final bills and time extensions.
School and site information, approved locations, technical scope and packages.
Estimates, tenders, contracts, contract values and contractor records.
Annual plans, allocations, receipts and field-level financial requests.
School-linked photographs, physical progress and water-quality screening.
Pre-final and final bills, measurements, approvals, returns and audit trail.
Time-extension requests, processing, approvals and imposed delay fines.
Management view
Instead of presenting the supplied internal screenshot publicly, this representative view captures the management logic visible in it.
Official implementation context
The government’s January–June 2025 environmental monitoring report recorded the following cumulative progress at that reporting point.
Public-facing figures are presented as rounded scale indicators. Internal dashboard values and screens are not reproduced.
Operational value
National totals could be traced into school, site, package, contract and field-level records.
Progress photographs and digital assets placed physical delivery beside the reported percentage.
Allocations, receipts, pre-final bills, final bills and approvals stayed within a connected workflow.
Time extensions, processing status, approvals and delay fines became visible to management.
After programme completion
With PEDP4 concluded, the connected dataset can support maintenance prioritization, water-quality follow-up, facility serviceability tracking, contractor performance analysis and evidence-based planning for the next education programme.
Rank facilities by age, defects, usage, geography and prior maintenance history.
Link screening and laboratory results to each school water source and its inspection history.
Move from “constructed” to whether water points and WASH blocks remain functional and accessible.
Use delivery, cost, delay and contractor evidence to improve targeting and implementation choices.
Source notes
*The completion milestone was supplied by the client for this case study. Public-facing programme figures are rounded.
From projects to institutional memory